The
Project Implementation Schedule is as follows:
1.
Procurement of Consulting Services: Sept.
2005-Dec. 2007 (27 months)
2.
Site Acquisition for Radar Facilities: Jan.
2008-Dec. 2009
3.
Consulting Services for Tendering, Detailed
Design and Construction Supervision: Feb. 2008-Sept.
2013 (68 months)
4.
Procurement of Goods and Services (Package I):
Feb. 2008-Dec. 2009 (22 months)
v
Review/updating of D/D, Pre-Qualification,
Finalization of Tender Document (incl. JBIC’s
concurrence): Feb. 2008-Jan 2009 (12 months)
v
Tendering & approval: Feb. 2009-Dec. 2009
(10 months)
5.
Construction/Installation Works for Package I:
Dec. 2009-June 2012 (30 months)
v
Construction of ATM Center: Dec. 2009-Feb.
2011 (15 months)
v
Equipment Manufacturing and Installation:
Dec. 2009-Mar. 2012 (28 months)
v
Acceptance test & Commissioning: Dec.
2011-May 2012 (6 months)
6.
Defects Liability Period for Package I:: June
2012-may 2013 (12 months)
7.
Detailed Engineering including Prequalification &
approval for Package II: Oct. 2008-May 2009 (8 months)
8.
Tendering and approval for Package II: May
2009-Mar. 2010 (10 months)
9.
Construction/Installation Works for Package II:
Feb. 2010-Jan. 2012 (24 months)
10.
Defects Liability Period for Package II: Mar.
2010-Mar. 2012 (12 months)

HERE to download Information Paper on